Painting, Trim, Exterior Soffit, Polishing the Concrete Floor

After a flurry of activity, Mom and Dad left for Michigan on October 18, staying about 10 days longer than they originally planned. They arrived on Labor Day weekend and hustled at the house every day. We’re so appreciative of their time and effort! It was a huge boost to our morale to wrap up some big projects while they were here!

Read More

Utility Time! Water and Sewer Tap + More Siding Installation

In Summit County, the building department has a moratorium on road permits between October 31-May 1, so it is super important for us to get the utility work done this fall. Like we talked about earlier in the month, we finally have power on site. Yes! And now we can happily say that the water line is done and we completed the sewer tap on September 23